Direccion | Inicio de Obra | Fin de Obra | Hoy | Dias | Finalizacion | Presupuesto | Emitido | a Emitir | Porcentaje de La Obra | Progreso de Obra | |
---|---|---|---|---|---|---|---|---|---|---|
Bacheo estructural | av. 59 3974 | 18/1/2021 | 27/6/2021 | 8/2/2023 | -591 | $2.000.000 | $1.800.000 | $200.000 | 90 | |
Bacheo estructural | av. 59 3975 | 19/1/2021 | 28/6/2021 | 8/2/2023 | -590 | $2.000.000 | $15.000 | $1.985.000 | 1 | |
Bacheo estructural | av. 59 3976 | 20/1/2021 | 29/6/2021 | 8/2/2023 | -589 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3977 | 21/1/2021 | 30/6/2021 | 8/2/2023 | -588 | $3.000.000 | $1.250.000 | $1.750.000 | 42 | |
Bacheo estructural | av. 59 3978 | 22/1/2021 | 1/7/2021 | 8/2/2023 | -587 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3979 | 23/1/2021 | 2/7/2021 | 8/2/2023 | -586 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3980 | 24/1/2021 | 3/7/2021 | 8/2/2023 | -585 | $2.000.000 | $200.000 | $1.800.000 | 10 | |
Bacheo estructural | av. 59 3981 | 25/1/2021 | 4/7/2021 | 8/2/2023 | -584 | $5.000.000 | $750.000 | $4.250.000 | 15 | |
Bacheo estructural | av. 59 3982 | 26/1/2021 | 5/7/2021 | 8/2/2023 | -583 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Norbbertoooooo | av. 59 3983 | 27/1/2021 | 6/7/2021 | 8/2/2023 | -582 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3984 | 28/1/2021 | 7/7/2021 | 8/2/2023 | -581 | $2.000.000 | $600.000 | $1.400.000 | 30 | |
Bacheo estructural | av. 59 3985 | 29/1/2021 | 8/7/2021 | 8/2/2023 | -580 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Urteaga el hoyo | av. 59 3986 | 30/1/2021 | 9/7/2021 | 8/2/2023 | -579 | $5.000.000 | $750.000 | $4.250.000 | 15 | |
Bacheo estructural | av. 59 3987 | 31/1/2021 | 10/7/2021 | 8/2/2023 | -578 | $2.000.000 | $350.000 | $1.650.000 | 18 | |
Bacheo estructural | av. 59 3988 | 1/2/2021 | 11/7/2021 | 8/2/2023 | -577 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Torta NEgra | av. 59 3989 | 2/2/2021 | 12/7/2021 | 8/2/2023 | -576 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3990 | 3/2/2021 | 13/7/2021 | 8/2/2023 | -575 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3991 | 4/2/2021 | 14/7/2021 | 8/2/2023 | -574 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3992 | 5/2/2021 | 15/7/2021 | 8/2/2023 | -573 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3993 | 6/2/2021 | 16/7/2021 | 8/2/2023 | -572 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3994 | 7/2/2021 | 17/7/2021 | 8/2/2023 | -571 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3995 | 8/2/2021 | 18/7/2021 | 8/2/2023 | -570 | $2.000.000 | $1.800.000 | $200.000 | 90 | |
Bacheo estructural | av. 59 3996 | 9/2/2021 | 19/7/2021 | 8/2/2023 | -569 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3997 | 10/2/2021 | 20/7/2021 | 8/2/2023 | -568 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3998 | 11/2/2021 | 21/7/2021 | 8/2/2023 | -567 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 3999 | 12/2/2021 | 22/7/2021 | 8/2/2023 | -566 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 4000 | 13/2/2021 | 23/7/2021 | 8/2/2023 | -565 | $2.000.000 | $750.000 | $1.250.000 | 38 | |
Bacheo estructural | av. 59 4001 | 14/2/2021 | 24/7/2021 | 8/2/2023 | -564 | $2.000.000 | $750.000 | $1.250.000 | 38 |